AI Certificates

CCDV-F Applications and Integration practice questions

33.1% of the CCDV-F exam. These worked examples come from free Form 1, with an explanation for every answer option.

D2 Applications and IntegrationCCDV-F · Form 1 · free

A product owner specifies that a new assistant must respond within 2 seconds and support 500 concurrent users. How should a developer classify these requirements?

  1. A

    Functional requirements, because they describe behavior that users directly observe

    Functional requirements describe what the system does — its features and behaviors; response time and concurrency describe how well it does it.

  2. B

    Non-functional requirements, because they constrain how well the system performsCorrect

    Response time and concurrent-user capacity are measurable quality attributes that constrain performance, the defining trait of non-functional requirements.

  3. C

    Business requirements, because they originate directly with the product owner

    Who states a requirement does not determine its category; business requirements express goals and outcomes, not measurable performance thresholds.

  4. D

    Design constraints, because they dictate which infrastructure components to purchase

    These figures constrain measurable qualities of the running system; by themselves they do not mandate any particular infrastructure choice.

The principle

Requirements that specify measurable qualities — latency, throughput, capacity — are non-functional; requirements that specify behaviors and features are functional, regardless of who states them.

D2 Applications and IntegrationCCDV-F · Form 1 · free

Larkspur Logistics wants Claude to summarize roughly 40,000 shipping-exception reports that accumulate overnight, with every summary visible in an internal dashboard by 6 a.m. No employee interacts with the system while it runs, and the solution architecture specifies a scheduled pipeline. Which infrastructure requirement follows most directly from these business requirements?

  1. A

    Low-latency streaming so each summary renders progressively as it is generated

    Streaming improves perceived latency for a watching user, but no one watches this pipeline run, so progressive rendering solves nothing here.

  2. B

    An autoscaling web tier sized for the surge of dashboard readers each morning

    Frontend scaling addresses read traffic after results already exist; the business requirement at risk is producing the results on time.

  3. C

    A priority queue that processes every report the moment it is filed

    Realtime per-report processing exceeds the stated need — the business requires completion by morning, not instant turnaround on each report.

  4. D

    Throughput sufficient to finish the full report volume by the deadlineCorrect

    The binding constraint is finishing tens of thousands of jobs inside a fixed window, which translates directly into a throughput requirement.

The principle

Derive infrastructure requirements from the binding business constraint — here, a completion deadline over a known volume — not from features that assume a different usage pattern.

D2 Applications and IntegrationCCDV-F · Form 1 · free

A team has completed requirements analysis and is now in the design stage of the systems life cycle. Which TWO activities belong in this stage, before implementation begins?

  1. A

    Running user acceptance tests against a completed release candidate

    User acceptance testing validates a built system; it belongs in the testing stage that follows implementation.

  2. B

    Specifying the data schemas and interfaces that components will shareCorrect

    Defining the schemas and interfaces components will share is core design work that must exist before developers implement against them.

  3. C

    Configuring production monitoring dashboards and on-call alert thresholds

    Monitoring and alerting are configured for a running system during deployment and operations, not during design.

  4. D

    Executing the cutover plan that migrates users to the new system

    Cutover is a deployment-stage activity; during design there is no system to migrate users onto.

  5. E

    Selecting the architectural patterns that the build will followCorrect

    Settling the architecture that implementation will follow is precisely what the design stage exists to do.

The principle

Each life-cycle stage produces artifacts the next stage consumes: design fixes structure and interfaces so that implementation, testing, deployment, and operations can each build on settled decisions.

Start free CCDV-F Form 1Applications and Integration